Paste filling machine specification
Build a user requirement specification around the real product condition, dose range, containers, cleaning method, utilities and expected production route.
Write the specification →Use these guides to turn a product and pack requirement into a testable machine specification, a controlled factory trial and a practical installation plan.

A paste filling project is easier to control when the product, pack, production target and acceptance method are written down before machine options are compared. The resources below organise that work without assuming one technology suits every paste.
Build a user requirement specification around the real product condition, dose range, containers, cleaning method, utilities and expected production route.
Write the specification →Plan a representative test using production product, real containers and a recorded measurement method before a configuration is fixed.
Prepare the sample trial →Turn agreed requirements into witnessed checks for dosing, cut-off, container handling, changeover, alarms and documentation before dispatch.
Plan the FAT →Check access, layout, product feed, electricity, compressed air, cleaning, drainage and integration before the machine arrives.
Prepare the site →Separate installation checks, dry running, wet commissioning, operator training and site acceptance so responsibilities remain clear.
Plan commissioning →Identify the product, pressure, temperature, moving machinery, cleaning and integrated-line hazards that need competent, site-specific review.
Review risk inputs →Use sequential samples, a stated measurement method and controlled product conditions instead of relying on an isolated good fill.
Plan fill checks →Calculate accepted packs per hour from filling, indexing, operator tasks, replenishment, capping, labelling and minor-stop recovery.
Plan realistic output →Map the wetted path, define safe access, record wear items and plan change parts before production depends on the machine.
Plan lifecycle support →The sequence can be adapted to the size of the project, but each stage should leave a clear record for the next one.
| Stage | Primary evidence | Decision |
|---|---|---|
| Application definition | Product at filling temperature, dose range, pack drawings or samples, closure, output and cleaning needs. | Which filling principles and machine formats are credible enough to test. |
| User requirement | Must-have, preferred and future requirements with stated acceptance methods. | What suppliers must price and what cannot be changed without approval. |
| Product trial | Sequential fill data, cut-off observations, product condition and container presentation. | Whether the proposed product path, valve, nozzle and feed arrangement are suitable. |
| Factory acceptance | Approved protocol, witnessed results, deviations, actions and document review. | Whether the machine is ready to dispatch or requires corrective work. |
| Site preparation | Approved layout, access route, utilities, product supply, downstream interfaces and safe working arrangements. | Whether installation can start without avoidable delay or rework. |
| Commissioning and handover | Dry and wet checks, site acceptance results, training records, manuals and outstanding-action list. | Whether the equipment is ready for controlled production use. |
Separate the filler base from product-feed equipment, containers, conveyors, capping, labelling, guarding, control interfaces, installation, commissioning, training and spare parts. A lower headline price can hide work that is still required before the first accepted pack is produced.
Use the paste filling machine buyer guide for overall selection, then use the specialist pages above to build the evidence required for your project.
Send the product, fill range, containers, closures, required accepted output and any current filling problem. Lancing can identify the information needed before a machine route is shortlisted.